PWD targets Nov 30 for Bhandari Bagh ROB as cost rises to Rs 56 Cr

PIONEER EDGE NEWS SERVICE/Dehradun

The Public Works Department (PWD) has set November 30 as the target to complete the Bhandari Bagh railway overbridge (ROB), whose estimated cost has risen from around Rs 43 crore to Rs 55.65 crore. The project, intended to provide direct connectivity between ISBT and GT Road and ease congestion at Saharanpur Chowk, is awaiting permission from the Railways for launching the bridge over the tracks.

The PWD assistant engineer Praveen Saxena told The Pioneer that the project was initially estimated to cost around Rs 43 crore, comprising Rs 33.62 crore for construction and approximately Rs 10 crore for shifting utilities. The revised estimate now stands at Rs 55.65 crore, an increase of around Rs 12.5 crore, he said.

The project was initially assigned to EPIL, which was later debarred. A fresh agreement was signed in 2021, but the previous agency completed only around 40 per cent of the work over the next four years. Saxena said that slow progress by the agency and delays in securing railway permissions has affected the project. The present agency signed the agreement on August 14, 2025 and began work around the same time. The original deadline was August 13, 2026, but the completion target has now been extended to November 30.

As per the PWD’s review report dated September 21, 2026, the ROB will be 578.71 metres long and have two lanes. Once completed, the bridge is expected to provide a direct route for commuters travelling from ISBT towards GT Road, reducing the need to take the longer route via Bhandari Bagh and easing congestion at Saharanpur Chowk.

Saxena said that the erection of the boosting girder had been completed. “Meanwhile, the project made progress after the Railways provided two short blocks, seven days after the block scheduled for October 27 was cancelled. During the blocks, the PWD installed one foundation raft near the railway tracks and placed one nine-metre-high iron BT column, completing around half of the BT column work,” he shared.  

The department will install the second BT column during the next railway block. Thereafter, the nearly 800-tonne bowstring steel bridge will be launched over the railway tracks using roller beam technology. The launching will be carried out during the final railway block and will require adequate time and permission from the Railways. Saxena said that they would go all-out to meet the November 30 deadline.